Tralee Regeneration

Tralee Town Council

Tralee Town Council

€800,000

3 months

Demolition

Tralee, Co. Kerry

 

 

The project involved the demolition of 105 houses in Mitchel’s Crescent area of Tralee.  The demolition was part of a 75 million euro regeneration project for Tralee.

 

The project involved large scale demolition work in close proximity to extremely busy areas.  Access to the site was restricted by adequate security arrangements.  The works involved a detailed investigation of all known services and a detailed investigation of the ground for unknown services.

 

 All demolition material was crushed on site for reuse within the recommended environmental guidelines.  Close cooperation was required with the community to mitigate against any adverse or unforeseen impacts.  A detailed traffic management plan was enforced for the duration of the works along with a comprehensive site boundary fence line

 

Tralee Regeneration

PROJECT DETAILS

PROJECT NAME

CLIENT

ARCHITECT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

SIZE

LOCATION

 

 

Fenit Port Development

Liebherr

Gottstein Architects

Brunner Consulting Engineers

--------------------------

3 months

Demolition

 

Fenit, Co. Kerry

 

 

 

 

Liebherr Crane Company exports to countries right around the globe from Fenit harbor.  The company entered a 99 year lease with Fenit Harbour Commissioners.

 

The demolition project was formerly the Fenit Sea World Visitors Centre and this was being demolished to accommodate a multi-million euro industrial building.  The scope of the works included, asbestos removal, diversion of existing port services, E.S.B substation demolition and the demolition of all structures on site.

 

All demolition material was crushed on site for re-use within the recommended environmental guidelines.  Close co-operation was required with Fenit Port and Liebherr for the delivery of large crane components to Fenit Port.  All works were carried out in a live port environment.

 

Fenit Port Development

PROJECT DETAILS

PROJECT NAME

CLIENT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

Evaporator Project

Mondelez Ireland

Malachy Walsh & Partners

------------------

3 months

Demolition

Rathmore, Co. Kerry

 

 

 

 

 

This project was the demolition of a disused boiler building.  This area of the factory is adjacent to the main operation with this remaining live and at full capacity for the entire project.  The demolition involved the removal of a 2 storey concrete structure with a structural steel truss roof.

 

The building needed to be detached from two adjoining buildings with interlocking walls and roofs.  Detailed monitoring of the adjacent buildings were maintained throughout the works.  All newly exposed walls to existing adjoining buildings were addressed for dampness and water ingress.  This work was undertaken in a live factory environment.

Evaporator Project

PROJECT DETAILS

PROJECT NAME

CLIENT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

Fitzgeralds Stadium

Kerry County Board

MRG Consulting Engineers

€250,000

6 weeks

Demolition

Killarney, Co. Kerry

 

 

 

 

 

 

Fitzgerald’s Stadium is located on Lewis Road in Killarney.

 

The project involved the demolition of the former dressing rooms to accommodate the construction of a new 5,000 spectator terrace other works included demolition of existing 4m high boundary walls to adjoining neighbors on Daltons Avenue, grub up existing hard standings, plant room demolitions including mechanical and electrical removal.

 

The stadium remained live during the execution of the contract and we took all necessary precautions to protect the staff and players from dust, excessive noise and other interference arising from the work.

.

Fitzgeralds Stadium

PROJECT DETAILS

PROJECT NAME

CLIENT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

 

Demolition Moyderwell Secondary School

Tralee Town Council

Tralee Town Council

€350,000

3 months

Demolition

Tralee, Co. Kerry

 

 

 

 

 

 

 

The site at Moyderwell which housed the Mercy Convent and St. Marys Secondary School were part of the Mitchels Crescent 75 million euro regeneration project.

 

The location of the site was in the Town Center so an extensive traffic management design and implementation was carried out before and during the project.

 

The works included asbestos removal, contaminated substances removal, contaminated ground removal, mechanical and electrical decommissioning and removal of over 3,000m2 2 storey structure.  All demolition material/concrete was crushed and screened on site for re-use within the recommended environmental guidelines.

 

 

Demolition Moyderwell Secondary School

PROJECT DETAILS

PROJECT NAME

CLIENT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

 

 

Warehouse/Commercial Building

Dairygold

Malachy Walsh & Partners

€275,000

2 months

Demolition

Ballincollig, Co. Cork

 

 

 

 

 

 

This project involved the demolition of 1700m2 warehouse/commercial building that consisted of a steel portal frame and R.C. walls and floors.

 

The demolition was to facilitate a new retail unit.  Works also included asbestos removal and the grubbing up of 4,000m2 of concrete yards.

PROJECT DETAILS

PROJECT NAME

CLIENT

ENGINEER

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

Cheestring Factory Kerry Group

Kerry Group

MRG Consulting Engineers

-----------------------

3 months

Demolition

Charleville, Co. Cork

 

 

 

 

This project was within the Kerry Group Plant in Charleville.  It involved the internal demolition of a 15 meter high R.C building including 3 R.C deck floors, columns, beam removal and large structural openings.

 

All temporary works design was carried out by Griffin Brothers.  Due to the nature of this project it was critical to protect uphold and maintain all adjoining services encountered during the works.  As this project was within a “live food production facility” we implemented a comprehensive dust and noise management plan.

 

Warehouse/Commercial Building

Cheestring Factory Kerry Group

PROJECT DETAILS

PROJECT NAME

CLIENT

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

 

 

Commercial Building

Kelliher Property Holdings

€230,000

2 months

Demolition

Town Center, Tralee, Co. Kerry

 

 

 

 

 

 

 

The property was a former car and tractor garage dating back to 1936 situated in Tralee Town Center, Denny Street, Tralee.  Access to the site was restricted to a small arched entrance where the project was located in a narrow lane adjacent to the buildings along Denny Street.

 

 

The structure was a 4 storey stone building with an attached garage containing R.C. walls and steel truss roof.  Adjoining the building on 2 elevations was a church that is in the record of protected structures.  Temporary shoring and underpinning to the foundations of the existing church were carried out and full reinstatement to the surrounding area.

 

An extensive traffic management plan and temporary works plan was designed and implemented.  Griffin Brothers worked closely with Tralee Town Council during the project.

Commercial Building

PROJECT DETAILS

PROJECT NAME

CLIENT

ARCHITECT

CONTRACT VALUE

CONTRACT DURATION

CATEGORY

LOCATION

 

 

 

 

 

 

Killarney Cinema Demolition

Cineplex

Tritschler Architects

€250,000

2 months

Demolition

Killarney, Co. Kerry

 

 

 

 

 

 

The project involved the demolition of the former Killarney cinema (Coopers), this was to accommodate the construction of a new five screen Cineplex.

 

The works involved large scale demolition over a 3,000m2 site in the heart of Killarney Town and in close proximity to extremely busy areas.  All demolition waste was removed from site and the ground was reinstated to a safe manner

 

 

Killarney Cinema Demolition

Copyright Griffin Brothers. All Rights Reserved.